How to make a roofing cake - a simple instruction for a difficult construction

Do you want to install a roofing cake under soft tiles, but do not know how? I will tell you how the roof pie is installed, without the involvement of highly qualified specialists. A step-by-step instruction will clearly confirm my words.

Roof construction is considered difficult, but some of the work can be done by unskilled workers.
Roof construction is considered difficult, but some of the work can be done by unskilled workers.

Roofing schemes

A roofing pie (roof) is a multi-layer structure in which each layer performs certain functions. For example:

  • roofing protects the building from atmospheric precipitation;
  • thermal insulation - from heat loss;
  • steam and waterproofing - from condensate.

Depending on the type of roof, the roof pie can be insulated or non-insulated.

Schematic image Description of roofing cake
table_pic_att14922046272 Scheme for an uninsulated (cold) roof. Such a roofing pie device does not have slope insulation, since heat-insulating materials in the attic are either not used at all, or are laid directly on the ceiling.

That is, the roof performs only the function of protecting the building from precipitation and wind.

table_pic_att14922046283 Scheme for insulated roof. In this case, the gap between the rafters is filled with heat and sound insulating material.

As a result, the insulated roof of which is made correctly, protects not only from precipitation, but also from heat loss. In such a scheme of pitched roofs, it is not necessary to lay out insulation on the floor.

Materials for a roofing pie

Illustration Description of materials
table_pic_att14922046304 Vapor barrier materials. These materials are used in order to prevent the penetration of moisture from inside the building into the insulation.

PVC membrane, geosynthetics, glassine, roofing material, roofing felt, spunbond, etc. are used as vapor barrier materials.

When arranging attic-type roofs, preference is given to elastic films of small thickness.

table_pic_att14922046335 Waterproofing materials. These materials pass steam, but do not pass water. Therefore, the waterproofing film is laid in the gap between the insulation and the roofing.

The purpose of waterproofing is to create a barrier between the insulation and condensate from the roofing. At the same time, steam from the insulation through such insulation is discharged into a ventilated gap.

table_pic_att14922046356 Thermal insulation materials. For laying in the gap between the rafters, insulation based on stone or mineral wool is used.

The effectiveness and price of thermal insulation are determined by the thickness and density of the materials used. For example, for the Moscow region, the composition of the roof provides for a layer of thermal insulation with a thickness of at least 20 cm.

table_pic_att14922046377 Roofing material range. These items are for sale:

  • hard coatings - slate, tiles, corrugated board, etc.;
  • soft coatings - rolled materials, bituminous tiles.

The device of the warmed roof with application of a bituminous tile

Illustrations Description of stages
table_pic_att14922046398 Installing a vapor barrier membrane. The vapor barrier layer is rolled out from the inside of the room perpendicular to the direction of the rafter legs.

If a membrane with a metallized layer is used, then this layer is lined inside the room.

The vapor barrier layer is shot with a stapler with your own hands to the rafters and glued with metallized tape.

table_pic_att14922046419 Joints and junctions of vapor barrier. At the junctions of adjacent strips, the vapor barrier is laid with an overlap of 15 cm.

Moreover, the strip located below should find its edge on the strip located above.

The overlap and adjoining of the vapor barrier to the gables is glued with a wide metallized adhesive tape.

table_pic_att149220464410 Vapor barrier lining from the attic. In order for the sealant to be firmly fixed and not to push through the vapor barrier, from the side of the attic, we fill a continuous crate onto the rafters. The boards are fastened transversely to the rafters in increments of 30 cm.
table_pic_att149220464611 Insulation installation. We unpack the package with mineral wool boards.

We lay the heat-insulating material in the gap between the rafters in two layers with an offset relative to each other. That is, the top layer should cover the joints between the plates in the bottom layer and prevent cold bridges.

table_pic_att149220464912 Installing the counter beam. Bars with a section of 50-50 mm are nailed across the rafters. The beam is attached in increments of 60 cm.

A mineral wool slab 50 mm thick is laid between the nailed beams. This slab eventually bridges the joints on the previous layers of insulation.

table_pic_att149220465213 Laying a vapor-diffusion (waterproofing) membrane. Waterproofing is lined with stripes in the direction from the roof overhang to the ridge, that is, from the bottom up.

The waterproofing strips are laid on the previous strip with an overlap of 15 cm. The overlap line is glued with high-quality double-sided tape, and then fastened with a stapler along the counter beam.

table_pic_att149220465414 Making a ventilation gap. On top of the membrane, in the direction of the rafters, a bar of 50-50 mm is laid out. A step of 30 cm is maintained between adjacent bars. The bars are nailed to the counter-beam.

Through each meter of timber, as shown in the photo, a passage is made so that adjacent ventilation ducts are combined and better ventilated.

table_pic_att149220465715 Rigid base for roofing. Approximate particle boards (OSB) with a thickness of at least 1 cm are laid out on top of the bar that forms the ventilation gap.

A compensation gap of 3-4 mm wide is left between adjacent fragments of plates.

table_pic_att149220465916 Installation of gutter holders. After the roofing pie is covered with a rigid base, brackets for the gutter are applied to the edge of the overhang.

The junction of the bracket to the overhang is outlined with a pencil, and then, along the intended perimeter, a chisel is selected with a chisel to the thickness of the bracket.

Brackets under the steel gutter are installed at intervals of 60 cm.

table_pic_att149220466117 Installing a drip. A dropper is an additional roofing element that is installed on the roof structure along the edge of the overhang.

Droppers are fastened with self-tapping screws for metal with a flat head.Silicone sealant is applied at the place where the two drip strips meet and an overlap of 10 cm is made.

Installation of the dripper is carried out after the drain brackets are installed.

table_pic_att149220466318 Installation of additional waterproofing. On top of the OSB boards, we lay rolled waterproofing.

The first strip is placed with an overlap of 3-5 cm on the edge of the dropper. To do this, double-sided tape is glued on top of the dropper.

The other edge of the waterproofing is fixed with roofing nails in increments of 30 cm. The second strip is laid with an overlap of 10 cm on the first strip.

A bituminous sealant is applied along the joint line.

table_pic_att149220466519 Laying the first row of shingles. We cut off the petals from the strip of tiles and remove the protective film.

We apply the prepared strip over the drip, so that the strip protrudes 1 cm forward beyond the waterproofing.

Bending the upper edge of the roofing, apply bituminous mastic. We nail the strip along the upper edge with roofing nails in increments of 20 cm.

table_pic_att149220466720 Laying the remaining tiles. The next fragments of the soft roof are laid with an overlap on the previous strip. That is, the petals of the second strip should reach the bottom edge of the first strip.

We fasten soft tiles along the upper edge and on the sides with special roofing nails no longer than 2.5 cm and with a flat head diameter of 9 mm.

table_pic_att149220466921 Laying tiles in the valley. If the slopes adjacent to the valley have an equal slope, the “pigtail” laying method is used. Tiles alternately from two sides start up on the valley.

If the roofing cake is made with a different slope of the slopes, the scoring method is used. The instruction is simple:

  • First, the tiles are laid on a slope with a small slope with a spade on the opposite slope, where the excess is trimmed;
  • From the opposite slope, tiles are started up and cut over the previously laid coating.
table_pic_att149220467122 Laying the ridge element. We cut off the petals from the strip of tiles, and cut the remaining strip into equal square pieces. We stuff these blanks onto the roofing cake along the ridge line for two nails.

As a result, each installed fragment should hang over the previously installed fragment.

Before laying a piece of tile, we apply bituminous mastic and heat the tile with a building hair dryer

.

table_pic_att149220467323 Ventilation installation. A hole is cut in the OSB for the base of the aerator. An anti-mosquito net is attached over the hole.

We apply a layer of bituminous mastic along the perimeter of the grid. We put an aerator on the mastic and fasten it to the sole with nails.

We apply mastic along the perimeter of the sole of the aerator, on which we put the tiles.

table_pic_att149220467524 Installation of feed-through elements. The sole of a passage element, for example, a ventilation pipe, is applied to the roof surface and outlined with a marker.

  • According to the markup, a hole is cut in the tiles and in the OSB. An anti-mosquito net is attached over the hole;
  • Bituminous mastic is applied to the mounting side of the sole of the passage element;
  • The sole of the passage element is applied to the perimeter of the hole in the roof and screwed with self-tapping screws.

Summing up

I am sure that now you will be able to independently insulate the internal volume of the truss system and form a high-quality roofing pie that will last a long time without regular repairs. I recommend watching the video in this article, and if you have any questions, ask in the comments.

Did the article help you?

Read also:  How to make a roof: instructions
Rating

Metal roof gutters - do-it-yourself installation in 6 stages
Flat Metal Trusses - Detailed Description and 2-Step Crafting Guide
Ruberoid - all brands, their types and characteristics
How inexpensive to cover the roof in the country - 5 economical options
Repair of the roof of an apartment building: the legal alphabet

We recommend reading:

Wall decoration with PVC panels